November 2013

November 21, 2013 11:04 pm
Excavation of the site between Mercy Street and Arnold Street side has reached the base and the removal of soil continues on the Hope Street side. So far 45,000 of the total 136,600 tonnes soil has been removed from site. more »

October 2013

October 29, 2013 10:56 pm
Excavation is on track with around 20,000 tonnes of clean fill removed from the site and 5,500 tonnes of contaminated soil safely disposed of. This means that the excavation is now around a fifteen per cent complete. Retention piles have more »

Construction update – enabling works completed

October 1, 2013 1:53 am
Enabling works $55m of projects were completed to prepare for the contruction of the new hospital. They were as follows: Ambulance Relocation This project involved the relocation of Ambulance Victoria services from Arnold Street, to strategic locations in the Bendigo more »