Construction update – March 2015

March 6, 2015 5:13 am
The formwork used to build the structure of the new Bendigo Hospital has been fully removed and the construction of internal structure continues apace. Since the start of the year the workforce has growth to just over 400 and it more »

Construction update – February 2015

January 28, 2015 2:43 am
The New Year has started strongly for the Bendigo Hospital Project construction team. The final stage of the structure, the steel frames on the roof, is well underway with around 60 per cent of the steel on the roof of more »

Construction update – November 2014

November 17, 2014 3:30 am
The structure of the new Bendigo Hospital will be finished before Christmas. The slab for the seventh floor of the hospital is being poured and the lower floors are being transformed by the installation of walls and services. Over 61,800 more »

Construction update – October 2014

October 14, 2014 11:10 pm
The structure of the new Bendigo Hospital is fast approaching completion with only 25 concrete pours remaining. On the shorter western structure there are 5 pours remaining and 20 on the eastern structure. The eastern side is currently at level more »

Construction update – September 2014

September 18, 2014 12:48 am
The second building in the Bendigo Hospital Project is almost complete with the final stages of work underway on the childcare centre in Yarrington House. The operator, Jenny’s ELC, are now undertaking landscaping and the fit out required enabling it more »

Construction update – August 2014

August 11, 2014 2:24 am
An important milestone was passed in the last month as more than 50 per cent of the concrete needed to construct the new Bendigo Hospital has been poured. There are now only 56 separate slabs to be poured before the more »