Construction update, November 2016

Providing a world-class hospital that can deliver high quality healthcare services for patients in the Loddon Mallee region for years to come is becoming, more than ever, a reality, as the new Bendigo Hospital reaches its crucial completion stage.
Stage One of this hospital construction project is substantially complete, and it is expected that the new Bendigo Hospital will open to the public in late January, 2017, following the completion of clinical equipment installation, staff training and a patient move day.

Right now, landscaping, equipment and furniture arrivals, readiness testing and operational preparedness are all proceeding during this important, completion and validation phase. Signage is also being applied throughout the building as a part of the wayfinding designs, and from the outside, the Bendigo Health logo and other main signs are now installed.

Workers
On the work site, there are approximately 150 workers, divided into three major roles: technical installations and testing, civil works and landscaping and construction finalisation.

Healthcare staff
Relocation planning, training and induction have been a major focus for staff, as Bendigo Health employees prepare for the move into the new facility. Recently staff members have attended forums to prepare them for site access. They learned safety protocols and what to expect in this new state-of-the-art building as it transitions from a construction site, into a functional hospital. This will ensure staff members are engaged with new technologies and familiar with the layout and designs in the new facility. This training prepares staff for the ‘transition’ phase which begins this month too, an important step that helps staff function effectively in their new environment, by working through ‘real life’ scenarios in the hospital.

Furniture and Equipment
Deliveries continue to keep the project teams busy, as trolleys, cabinets, monitor stands, recliner chairs and many more items are received, being then quickly dispatched to their appropriate location. Testing and tagging of equipment is taking place, a strong signal that the project’s operational opening is moving closer.

Landscaping
Landscaping is progressing at a rapid rate, and dozens of advanced trees, freshly transplanted, now flank the new building. Courtyards throughout the new hospital, both internal and external are now completed.

Heritage buildings
In the historic precinct, which primarily fronts onto 100 Barnard Street, the works to the Anne Caudle Centre, Concert Hall, West Wing and other heritage buildings are in the process of completion, as part of Bendigo Health’s works plan. Approximately 12 workers are on site for these works, which has included installing a new entrance, including a lift and disability toilets, to the Anne Caudle Centre building and also refurbishing the West Wing, in preparation for repurposing into office workplaces for Bendigo Health staff.

Important roadworks
Roadworks around the Bendigo Hospital precinct have been in full swing this month, in both Arnold and Lucan Streets. All works were completed on November 15, and were carried out to upgrade kerbs, traffic islands and road surfaces. Full details of these roadworks are featured in October’s Construction Update.

Technical completion milestone achieved
The Bendigo Hospital Project has achieved early technical completion for Stage One this month, on November 14, 2016. More details about this important milestone will be included in early December’s Construction Update and an upcoming media release.

External construction progress can still be monitored on the webcam available at this Bendigo Hospital Project website home page.